WORKERS VILLAGE CAMP ERECTION (CIVIL & INSTALLATION) WORKS NLNG T7 PROJECT

STATUS: ON-GOING

BACKGROUND: TRAIN7 PROJECT
Nigeria LNG Train7 project is an ongoing expansion of the Nigeria LNG Terminal at Bonny Island, Nigeria, which currently has a total of six operational LNG processing units, four 84,200m³ LNG storage tanks, four 65,000m³ refrigerated storage tanks, and three 36,000m³ condensate storage tanks.
The Nigeria LNG Train7 project will add a seventh LNG processing unit with a production capacity of 4.2Mtpa and supporting infrastructure including an 84,200m³ storage tank, a 36,000m³ condensate tank, and three gas turbine generators at the terminal.
Upon completion, the Nigeria LNG Train7 project will increase the Nigeria LNG Terminal production capacity by 35% from the current 22mtpa to 30mtpa.

SCOPE OF WORK:
In February 2022, Horatio Limited was awarded the contract for the Workers Village Camp Erection through Saipem/Daewoo the Contracting Company for the Train7 project.
Horatio Limited’s scope of works includes but not limited to all Civil Works, Caravan and other Erection Works, Plumbing, Piping Works and Electrical Works.
The project is expected to last for Fourteen (14) months elapsing in April 2023.
  • slide
  • slide
  • slide
  • slide
  • slide
  • slide
  • slide
  • slide
  • slide
  • slide
  • slide